Public consultation

Public consultation

As a result of TI-Link’s designation as a Project of Mutual Interest (PMI), a strategic cross-border infrastructure project between EU and non-EU countries, a public consultation is required under Regulation (EU) 2022/869.

What is the Public Consultation?

The Public Consultation is a participatory process where citizens can provide input, feedback and suggestions to improve and refine the project design.

Although the final decision on the project lies with the Ministry of the Environment and Energy Security (MASE), the competent authority responsible for the overall permitting procedure, the public consultation is a key element in developing a project that is sustainable and suited to the local area.

The public consultation consisted of a series of public meetings, starting on 13 May 2026, in the municipalities affected by the proposed locations. At these meetings, Zhero’s technical team presented the project in detail and answered questions, while also gathering input on the project.

From 21 May to 23 July 2026, a dedicated period for written submissions was open, during which further comments could be sent to Zhero. To conclude, an online meeting was held on 18 September 2026 to present the contributions received, the related technical considerations and the locations identified through dialogue with local communities.

Following the change to TI-Link’s connection solution to the National Transmission Grid (RTN) requested by Terna, Zhero applied to the Ministry of the Environment and Energy Security (MASE) for an extension of the public consultation process, in order to examine the new connection arrangement, which includes a new substation for connection to the RTN.

The extension, involving the municipalities of Campiglia Marittima and Suvereto, includes a new information meeting for residents on 6 November and a 30-day period, from 6 November to 6 December, for submitting comments. A final online meeting will be held at the end of this phase, on 14 December.

The results of the entire process will then be set out in a final report on the consultation outcomes, which Zhero will submit to MASE to start the permitting phase.

Further details on how the public consultation is carried out are provided in the Information Leaflet, which contains the Consultation Plan.

La Consultazione pubblica ha preso ufficialmente avvio il 13 maggio 2026, con un primo appuntamento online di presentazione dell’opera, a cui sono seguiti incontri in presenza nei comuni interessati dalle ipotesi localizzative di TI-Link. Il 18 settembre 2026 si è tenuto l’incontro online di restituzione degli esiti della prima fase, secondo quanto previsto dal Calendario degli incontri di Consultazione pubblica approvato dal MASE.

Nel mese di aprile 2026 si sono svolti alcuni incontri preliminari alla Consultazione, organizzati nell’ambito del percorso di Participatory design process con le amministrazioni comunali, per consentire a cittadini, portatori di interesse e soggetti interessati di conoscere il progetto e confrontarsi con i tecnici di Zhero prima dell’avvio formale del percorso.

Following the change to TI-Link’s connection solution to the National Transmission Grid (RTN) introduced at Terna’s request, an extension of the public consultation was requested to examine the new connection arrangement, which includes a new substation for connection to the RTN. The additional phase will involve the municipalities of Campiglia Marittima and Suvereto, with a new information meeting on 6 November 2026, a period for written submissions from 6 November to 6 December and a final meeting on 14 December 2026.

The public consultation officially began on 13 May 2026 with an online presentation of the project, followed by in-person meetings in the municipalities affected by TI-Link’s proposed locations. On 18 September 2026, an online meeting was held to present the outcomes of the first phase, in line with the public consultation meeting schedule approved by MASE.

In April 2026, a number of meetings were held ahead of the consultation as part of the participatory design process with the municipal administrations, giving citizens, stakeholders and other interested parties the opportunity to learn about the project and talk to Zhero’s technical team before the formal process began.

The public consultation covers the Italian section of the route, from the 12-nautical-mile limit to the RTN connection node in Suvereto. Interested parties may therefore submit comments on:

  • the route of the subsea and onshore cables;
  • the landfall locations for the cables and electrodes;
  • the location of the converter station.

In addition, questions, concerns and requests for clarification may be submitted on any aspect of the project, from design and construction to commissioning, as well as general comments.

As part of the extension of the consultation process, comments may also be submitted on the location of the new 380 kV substation connecting TI-Link to the RTN, requested by Terna following the change to the connection solution.

All contributions will be carefully reviewed and will receive a specific response from Zhero.

La consultazione pubblica

How can I attend the public consultation meetings?

In agreement with the municipalities of Campiglia Marittima, Castagneto Carducci, Follonica, Piombino, San Vincenzo and Suvereto, the following schedule of public consultation meetings, approved by the Ministry of the Environment and Energy Security (MASE), has been drawn up.

Incontro 22 aprile | Suvereto e Campiglia Marittima
Sala SEFI, Largo della Fiera 3, Venturina Terme, Campiglia Marittima
22 Apr 2026
10:00
20:00

Comuni interessati: Suvereto, Campiglia Marittima

Dalle ore 10.00 alle 13.00
Dalle ore 17.00 alle 20.00

22
APR
Incontro 23 aprile | Castagneto Carducci
Cinema Ariston di Donoratico, Via della Repubblica, Castagneto Carducci
23 Apr 2026
10:00
20:00

Comune interessato: Castagneto Carducci

Dalle ore 10.00 alle 13.00
Dalle ore 17.00 alle 20.00

23
APR
Incontro 27 aprile | Piombino
Centro Giovani di Piombino, Viale della Resistenza n.4, Piombino
27 Apr 2026
10:00
20:00

Comune interessato: Piombino

Dalle ore 10.00 alle 13.00
Dalle ore 17.00 alle 20.00

27
APR
Incontro 28 aprile | San Vincenzo
San Vincenzo
28 Apr 2026
10:00
20:00

Comune interessato: San Vincenzo

Dalle ore 10.00 alle 13.00
Dalle ore 17.00 alle 20.00

28
APR
Incontro 29 aprile | Follonica
Sala ex Casello Idraulico, via Roma, 45-46, Follonica
29 Apr 2026
10:00
13:00

Comune interessato: Follonica

Dalle ore 10.00 alle 13.00

29
APR
Online
Incontro 13 maggio | Plenaria online
Online
13 May 2026
18:00

Dalle ore 18:00 alle 20:00

Download guida Teams

13
MAY
Incontro 14 maggio | Campiglia Marittima e Suvereto
Sala La Pira, Largo della Fiera 5, Campiglia Marittima
14 May 2026
09:00

Open day: dalle ore 09.00 alle 17.00 

Presentazione progetto e Q&A: dalle 17.00 alle 20.00

14
MAY
Incontro 19 maggio | Follonica
Sala Tirreno, Via Bicocchi 53/a, Follonica
19 May 2026
09:00

Open day: dalle ore 09.00 alle 17.00

Presentazione progetto e Q&A: dalle 17.00 alle 20.00

19
MAY
Incontro 20 maggio | Castagneto Carducci
Cinema Ariston di Donoratico, Via della Repubblica, Castagneto Carducci
20 May 2026
09:00

Open day: dalle ore 09.00 alle 11.00

Presentazione progetto e Q&A: dalle 11.00 alle 13.00

20
MAY
Incontro 20 maggio | San Vincenzo
Sala Consiliare della Torre, Via della Torre 10, San Vincenzo
20 May 2026
15:00

Open day: dalle ore 15.00 alle 17.00

Presentazione progetto e Q&A: dalle 17.00 alle 20.00

20
MAY
Incontro 21 maggio | Piombino
Centro Giovani di Piombino, Viale della Resistenza n.4, Piombino
21 May 2026
09:00

Open day: dalle ore 09.00 alle 17.00

Presentazione progetto e Q&A: dalle 17.00 alle 20.00

21
MAY
Meeting 16 june | Campiglia Marittima and Suvereto
Sala La Pira, Largo della Fiera 5, Venturina Terme
16 Jun 2026
17:30

From 17.30 to 20.00

16
JUN
Meeting 17 june | Follonica
Sala Tirreno, Via Bicocchi 53/a, Follonica
17 Jun 2026
17:00

From 17.00 to 20.00

17
JUN
Meeting 18 june | Castagneto Carducci
Cinema Ariston di Donoratico, Via della Repubblica, Castagneto Carducci
18 Jun 2026
17:30

From 17.30 to 20.00

18
JUN
Meeting 19 june | Piombino
Centro Giovani di Piombino, Viale della Resistenza n.4, Piombino
19 Jun 2026
17:00

From 17.00 to 19.00

19
JUN
Meeting 13 july | Campiglia Marittima and Suvereto
Sala La Pira, Largo della Fiera 5, Venturina Terme
13 Jul 2026
17:30

From 17.30 to 20.00

13
JUL
Meeting 14 july | Follonica
Sala Tirreno, Via Bicocchi 53/a, Follonica
14 Jul 2026
17:00

From 17.00 to 20.00

14
JUL
Meeting 15 july | San Vincenzo
Sala Consiliare della Torre, Via della Torre 10, San Vincenzo
15 Jul 2026
15:00

From 15.00 to 17.00

15
JUL
Meeting 16 july | Piombino
Centro Giovani di Piombino, Viale della Resistenza n.4, Piombino
16 Jul 2026
17:00

From 17.00 to 19.00

16
JUL
Online
Incontro 18 settembre | Plenaria online
Online
18 Sep 2026
18:00

Dalle ore 18:00 alle 20:00

Download guida Teams

18
SEP
Incontro 06 novembre | Campiglia Marittima e Suvereto
Sala La Pira, Largo della Fiera 5, Venturina Terme
06 Nov 2026
09:00

Open day informativo
Dalle ore 09.00 alle 20.00

06
NOV

How can I submit comments on the project?

To submit your comments, simply send an email to:

info@ti-link.it

Alternatively, you can fill in the form below.

Progettazione partecipata

Participatory design process

The public consultation was built on the outcomes of the participatory design process, a working methodology adopted by Zhero from the earliest stages of project development. This approach is based on early engagement with competent national, regional and local authorities and institutions. The objective is to share the main project options to be submitted to public consultation and to define, in a coordinated manner, the tools and timeline of the participatory process.

Stakeholders involved in the process include the Ministry of the Environment and Energy Security (MASE), ISPRA, the National Superintendency for Underwater Cultural Heritage, Terna, Legambiente, WWF, Italia Nostra, the Tuscany Region, the Valdarno Inferiore Civil Engineering Authority, the Superintendencies for Archaeology, Fine Arts and Landscape for the provinces of Pisa and Livorno and for the province of Grosseto, ARPAT and the municipalities of Campiglia Marittima, Castagneto Carducci, Follonica, Piombino, San Vincenzo and Suvereto.

Through dedicated technical working groups and stakeholder meetings, Zhero incorporated the contributions received into the preparation of the Non-Technical Summary and the Information Leaflet, which were subsequently submitted to MASE for approval and the formal launch of the public consultation process.

Materials

Information Leaflet