Vai al contenuto principale

Project overview

From the Italian landfall to the national electricity grid

The route in Italy

In Italy, the project proposals focus on the municipalities surrounding Terna’s Suvereto substation, designated by the national transmission system operator as the grid connection point. This choice reflects the Suvereto node’s capacity to host the interconnection’s power, its position relative to major electricity demand centres and the need to avoid overloading grids in central and southern Italy, which are already congested due to the high concentration of renewable generation plants in those areas.

The Italian route of the infrastructure, defined through dialogue with the local communities concerned, includes a landfall point for the subsea cables in the Gulf of Follonica area, underground cables laid along existing roads to reach a new converter station, a sea electrode ensuring the safety and reliability of the interconnection and, following the change to the connection solution requested by Terna, a new 380 kV substation dedicated to connecting TI-Link to the National Transmission Grid (RTN).

The landfall sites for the subsea pole cables and the electrode, as well as the converter station site, were also identified through a preliminary and voluntary participatory design process with citizens, organisations and institutions. They were then submitted to public consultation, the formal citizen participation tool provided for by current legislation as part of the permitting process before the Ministry of the Environment and Energy Security (MASE).

The location of the new 380 kV substation for connection to the national grid is still under consultation, which has been extended following a substantial change to the connection solution requested by the RTN operator.

For more information on the proposed locations, please see the interactive map.

The marine route

From the coastline to a depth of approximately 1,000 metres, the submarine cables will be buried beneath the seabed at varying burial depths, depending on geological and environmental conditions. This approach is designed to balance protection against potential human interference with permitted fishing activities. At depths beyond 1,000 metres, where bottom trawling and anchoring activities are minimal, the cables will be laid directly on the seabed without burial requirements.

To minimise environmental impact on the marine ecosystem, installation techniques such as jetting will be used in sandy seabeds, while mechanical trenching or rock dumping will be applied in rocky or irregular seabed conditions. At the landfall points, the connection between submarine and onshore cables will be carried out using HDD (Horizontal Directional Drilling), a trenchless technique that avoids open-cut trenching, both offshore and onshore.

The cables will be manufactured using advanced insulating materials such as mass-impregnated paper or cross-linked polyethylene (XLPE), selected according to the characteristics of each section to ensure safety, reliability and environmental compatibility. The infrastructure is designed for a minimum operational lifetime of 40 years. The interconnection may be developed in progressive phases, starting with an initial installed capacity, followed by increases up to the planned 2 GW.

of subsea interconnection
0 km
of interconnection capacity
0 GW
From renewable generation to transmission to Italy

The route in Tunisia

The project is designed around the development of a large-scale integrated renewable energy hub in Tunisia’s desert regions, with abundant solar and wind resources.

The energy mix combines utility-scale solar PV, onshore wind generation and battery energy storage systems (BESS), targeting an overall installed capacity of at least 5 GW. This hybrid configuration is intended to optimise resource complementarity and deliver a more balanced and reliable generation profile.

Certified renewable electricity generated by the plants will be transmitted to the Tunisian coast through dedicated high-voltage transmission infrastructure, developed by Zhero in close cooperation with STEG. The transmission corridor will also include intermediate connection points to support integration with the local Tunisian grid. From the coast, power will be exported across the Mediterranean through high-voltage direct current (HVDC) submarine interconnectors, enabling efficient long-distance transmission while minimising electrical losses.

The integration of large-scale BESS technology will allow the system to achieve a semi-baseload renewable generation profile — a capability that is difficult to replicate in Italy and across most of Europe. This will make it possible to supply low-carbon electricity even during traditionally hard-to-abate periods, supporting deeper decarbonisation of the power sector. As with the interconnection infrastructure, the renewable generation hub can also be implemented in phases, allowing capacity to be commissioned progressively over time.

Project timeline

The timeline is indicative and subject to change based on the progress of the permitting process.

Materials

Non Technical Summary