Project overview
L’approdo dei quattro cavi marini di polo nel Golfo di Follonica Following the public consultation process, the landfall for the four subsea pole cables in the Gulf of Follonica has been identified within the municipality of Follonica. The preferred option is the municipal car park near Camping Tahiti, while a backup option has been selected nearby, close to a reedbed. parcheggio comunale in prossimità del Camping Tahiti, mentre un’ipotesi di riserva è stata individuata nelle vicinanze, in prossimità di un canneto.
The final choice will be based on marine surveys scheduled for 2027, which will assess the presence and condition of Posidonia seagrass meadows and identify the solution that minimises environmental impact. The landfall will be built using low-impact techniques such as horizontal directional drilling (HDD), which avoid open-cut excavation and limit disturbance to the dune and beach. Construction activities will also be scheduled in agreement with the local authorities, taking the bathing season into account.
The converter station converts direct current (DC) into alternating current (AC), so that the power can be fed into the National Transmission Grid (RTN).
Following the public consultation process, the converter station has been sited in the municipality of Campiglia Marittima, specifically in the Campo alla Croce industrial area in Venturina.
The site was identified together with the municipal administration through a participatory design process, as it was considered consistent with current land-use plans and compatible with the surrounding landscape and agricultural setting. During detailed design, the location was further refined to include part of Venturina’s PIP area, a zone designated for industrial and commercial development.
The sea electrode is a key component for the safety and reliability of the HVDC interconnection, and can come into operation in the event of faults or during maintenance. It consists of a metal grid buried in the seabed, located offshore approximately 7–8 km from the coast, at a depth of between 35 and 50 metres.
Following the public consultation process, the electrode landfall has been identified within the municipality of San Vincenzo, specifically in the municipal car park on Via Tridentina. A backup option has also been selected in the municipality of Castagneto Carducci, near the ANAS road junction. The final location will be determined on the basis of marine surveys scheduled for 2027, which will assess the condition of Posidonia seagrass meadows and minimise impacts on the marine and coastal ecosystem.
Low-impact construction techniques such as horizontal directional drilling (HDD) will also be used for the electrode landfall. In addition, construction activities will be scheduled in agreement with the local authorities, taking the tourist season into account.
Following a substantial change to TI-Link’s connection solution to the National Transmission Grid (RTN), requested by Terna, Zhero applied to the Ministry of the Environment and Energy Security (MASE) for an extension of the public consultation process, in order to examine the new connection arrangement in more detail. Specifically, Terna has requested the construction of a new 380 kV substation dedicated exclusively to the connection of TI-Link.
The new substation, which is separate from the project’s converter station, will not include the buildings and equipment used for conversion, but will house eight bays required for connection to the RTN. Four will be used for the double in-out connection to the 380 kV “Suvereto–Piombino” RTN lines, two for the bus coupler and two for the connection of the plant.
The space required, estimated at around 3–4 hectares, calls for further assessment of possible locations and their local impacts, particularly with the municipalities of Campiglia Marittima and Suvereto, which are concerned respectively by TI-Link’s new converter station and Terna’s existing substation.
The options under consideration for the new connection substation fall within the areas already covered by the public consultation for the converter station, in the Campo alla Croce industrial area. The final location will be determined at the end of the consultation process, based on input from dialogue with local communities and authorities.
The Terna substation in Suvereto has been identified by Terna, the Italian transmission system operator, as the grid connection point where electricity imported from Tunisia will be injected into the Italian National Transmission Grid (RTN). From this node, the energy will be transmitted across the network to major load centres and demand hubs throughout Italy.
The renewable energy generation park in the Tunisian desert will consist of photovoltaic and wind power plants, with a total installed capacity of approximately 5 GW and an estimated annual production of around 15.5 TWh of certified renewable electricity. The project will be developed in the southern desert region of Tunisia, an area identified for its exceptional solar and wind resources. The final site selection is still under assessment by the Tunisian authorities.
Per poter essere trasportata su lunghe distanze, l’energia prodotta dovrà essere trasformata da corrente alternata, in corrente continua: la tecnologia più sicura ed efficace per attraversare il Mar Mediterraneo, in quanto in grado di limitare perdite e dispersioni. A tal fine, sarà necessaria una stazione di conversione, a pochi chilometri dalla costa, dove l’energia si immetterà per continuare il suo percorso verso l’Italia. La localizzazione della stazione è in fase di studio e sarà oggetto di approfondimenti da parte delle autorità tunisine.
From the northern coast, the energy will continue its transmission along the Tunisian shoreline. From there, it will be exported across the Mediterranean Sea over a distance of approximately 600 km to Italy via submarine cables. The exact landfall study area is still under evaluation by the Tunisian authorities.
The route in Italy
In Italy, the project proposals focus on the municipalities surrounding Terna’s Suvereto substation, designated by the national transmission system operator as the grid connection point. This choice reflects the Suvereto node’s capacity to host the interconnection’s power, its position relative to major electricity demand centres and the need to avoid overloading grids in central and southern Italy, which are already congested due to the high concentration of renewable generation plants in those areas.
The Italian route of the infrastructure, defined through dialogue with the local communities concerned, includes a landfall point for the subsea cables in the Gulf of Follonica area, underground cables laid along existing roads to reach a new converter station, a sea electrode ensuring the safety and reliability of the interconnection and, following the change to the connection solution requested by Terna, a new 380 kV substation dedicated to connecting TI-Link to the National Transmission Grid (RTN).
The landfall sites for the subsea pole cables and the electrode, as well as the converter station site, were also identified through a preliminary and voluntary participatory design process with citizens, organisations and institutions. They were then submitted to public consultation, the formal citizen participation tool provided for by current legislation as part of the permitting process before the Ministry of the Environment and Energy Security (MASE).
The location of the new 380 kV substation for connection to the national grid is still under consultation, which has been extended following a substantial change to the connection solution requested by the RTN operator.
For more information on the proposed locations, please see the interactive map.
The marine route
From the coastline to a depth of approximately 1,000 metres, the submarine cables will be buried beneath the seabed at varying burial depths, depending on geological and environmental conditions. This approach is designed to balance protection against potential human interference with permitted fishing activities. At depths beyond 1,000 metres, where bottom trawling and anchoring activities are minimal, the cables will be laid directly on the seabed without burial requirements.
To minimise environmental impact on the marine ecosystem, installation techniques such as jetting will be used in sandy seabeds, while mechanical trenching or rock dumping will be applied in rocky or irregular seabed conditions. At the landfall points, the connection between submarine and onshore cables will be carried out using HDD (Horizontal Directional Drilling), a trenchless technique that avoids open-cut trenching, both offshore and onshore.
The cables will be manufactured using advanced insulating materials such as mass-impregnated paper or cross-linked polyethylene (XLPE), selected according to the characteristics of each section to ensure safety, reliability and environmental compatibility. The infrastructure is designed for a minimum operational lifetime of 40 years. The interconnection may be developed in progressive phases, starting with an initial installed capacity, followed by increases up to the planned 2 GW.
The route in Tunisia
The project is designed around the development of a large-scale integrated renewable energy hub in Tunisia’s desert regions, with abundant solar and wind resources.
The energy mix combines utility-scale solar PV, onshore wind generation and battery energy storage systems (BESS), targeting an overall installed capacity of at least 5 GW. This hybrid configuration is intended to optimise resource complementarity and deliver a more balanced and reliable generation profile.
Certified renewable electricity generated by the plants will be transmitted to the Tunisian coast through dedicated high-voltage transmission infrastructure, developed by Zhero in close cooperation with STEG. The transmission corridor will also include intermediate connection points to support integration with the local Tunisian grid. From the coast, power will be exported across the Mediterranean through high-voltage direct current (HVDC) submarine interconnectors, enabling efficient long-distance transmission while minimising electrical losses.
The integration of large-scale BESS technology will allow the system to achieve a semi-baseload renewable generation profile — a capability that is difficult to replicate in Italy and across most of Europe. This will make it possible to supply low-carbon electricity even during traditionally hard-to-abate periods, supporting deeper decarbonisation of the power sector. As with the interconnection infrastructure, the renewable generation hub can also be implemented in phases, allowing capacity to be commissioned progressively over time.
Project timeline
The timeline is indicative and subject to change based on the progress of the permitting process.